Planning resid. Enphase system. (No batteries)
City hinting that we need an ACD or Rapid Shutdown Initiation Device (RSID) on front of house.
They wrote:
"There is also a rapid shutdown initiation device to consider according to 690.12(C).
This device is defined as being located at a readily accessible location."
However, all (E) Meter, main panels and service discos are in garage.
Can the RSID just be the (E) service disco as per usual?
PS I am tieing PV into 3rd floor sub panel, just under roof...............and have no intention of running all teh circuits down to ground on front (ugly too) .
City hinting that we need an ACD or Rapid Shutdown Initiation Device (RSID) on front of house.
They wrote:
"There is also a rapid shutdown initiation device to consider according to 690.12(C).
This device is defined as being located at a readily accessible location."
However, all (E) Meter, main panels and service discos are in garage.
Can the RSID just be the (E) service disco as per usual?
PS I am tieing PV into 3rd floor sub panel, just under roof...............and have no intention of running all teh circuits down to ground on front (ugly too) .