I can not find anything in the NEC that states that a panel can not be installed in a kitchen. My Employer for years has belived that this can not happen.
The job is a fire job for Izzy's pizza in Newberg Oregon and there are 3, 3 phase panels located in the kitchen. The only argument that I can see is that it could passably be argured a damp location because the area is for washing dishes.
The city inspector says that the location of the panels is fine.
Any comments other than AHJ???
Combo Inspectors do not always know what they are looking at.
The job is a fire job for Izzy's pizza in Newberg Oregon and there are 3, 3 phase panels located in the kitchen. The only argument that I can see is that it could passably be argured a damp location because the area is for washing dishes.
The city inspector says that the location of the panels is fine.
Any comments other than AHJ???
Combo Inspectors do not always know what they are looking at.