Is it an NEC requirement that IF a connection to footer steel(stub up) is available, it MUST be connected to any other available or installed electrode?. I have a job where we installed 2 rods 6ft apart, not realizing a connection to the footer steel existed. The AHJ says it must be used. Is this correct?