The project is a new school with a poured footing and foundation. We installed the standard 20' of
#4 with the approved clamp to the rebar.
The footing was poured in approx 12 seperate pours
with rebar extending from section to section.
The inspector states it's the electrical contractors responsability to install a bond jumper from section to section and provide
a bonding certificate for all 12 sections. Also,
each section of footing was inspected by the engineer and the local building official.
#4 with the approved clamp to the rebar.
The footing was poured in approx 12 seperate pours
with rebar extending from section to section.
The inspector states it's the electrical contractors responsability to install a bond jumper from section to section and provide
a bonding certificate for all 12 sections. Also,
each section of footing was inspected by the engineer and the local building official.