The bonding and ground path must be continuous. The continuity must not rely on meters, filters, or other devices. A jumper must be installed. IAEI states that the ground path should be permanent.
?? Is each break in pipe such as at each valve, union, coupling, etc. then required to have a jumper cable throughout the entire facility. Is a pipe connection which the manufacturer states is electrically continuous without a jumper acceptable? UL does note test pipe fittings for continuity as far as I know.
?? Is each break in pipe such as at each valve, union, coupling, etc. then required to have a jumper cable throughout the entire facility. Is a pipe connection which the manufacturer states is electrically continuous without a jumper acceptable? UL does note test pipe fittings for continuity as far as I know.