Can I run this by somebody?
4- three phase inverters with 24 amps per leg. I would put in 4- 30amp three pole breakers and install a 125amp rated three phase panelboard.
Does this sound right?
Thanks ahead of time for your help!
4- three phase inverters with 24 amps per leg. I would put in 4- 30amp three pole breakers and install a 125amp rated three phase panelboard.
Does this sound right?
Thanks ahead of time for your help!