Hi everyone,
I have a large install in South Florida to bid on where they convert a warehouse to night club.
The ceiling is going to be open grid (8? x 8? squares) suspended @ +12?-0? above finish floor, open to structure above.
The total height is 26'.
I am planning to recommend installing cable trays above the grid for my cameras wiring and A/V cabling to make life easier for everyone.
My question is if it will be code violation to mount my cameras to the bottom of the tray, or dropping a 24" long EMT stub from the cable tray to a gang box.
The cameras are very light, maybe 2 LBs max, I really doubt it will affect the tray system.
Will appreciate any comments thanks.
I have a large install in South Florida to bid on where they convert a warehouse to night club.
The ceiling is going to be open grid (8? x 8? squares) suspended @ +12?-0? above finish floor, open to structure above.
The total height is 26'.
I am planning to recommend installing cable trays above the grid for my cameras wiring and A/V cabling to make life easier for everyone.
My question is if it will be code violation to mount my cameras to the bottom of the tray, or dropping a 24" long EMT stub from the cable tray to a gang box.
The cameras are very light, maybe 2 LBs max, I really doubt it will affect the tray system.
Will appreciate any comments thanks.