transman2
Senior Member
- Location
- Brooklet,Ga.
I have an electrical contractor on a large job that had to install a ground ring and ground rods around footing foundations but it was stated in the SOW that the pigtale from the footing rebar would be in place and complete before the work described in the contract begins. This seems unusual to me that the Engineer would have worded it this way. So 2 years later and no rebar grounded because no one mentioned it was missed or not done. The drawing show it should be done but the EC did not mention that no one installed the pigtale for them to tie to.
Is it the responsibility of the EC to let the customer know it was left out and they didnt do it?
Is it the responsibility of the EC to let the customer know it was left out and they didnt do it?